Port guide · Da Nang · Tien Sa · Lien Chieu · Chu Lai · Project cargo
Da Nang port is the main sea gate for central Vietnam: Tien Sa handled about 850,000 TEU and more than 15 million tonnes in 2025. This guide covers which terminal your cargo will use, what the new Lien Chieu port changes, and how heavy units actually move on Da Nang’s roads, with photos from our own night girder moves in the city.
For freight agents, carriers’ OOG desks and EPC contractors with sites in central Vietnam. · Jump to the road leg

The usual problem with a Da Nang port booking is not the quay. It is the road between the quay and the site. A transformer, a girder or a crusher frame lands at Tien Sa on the Son Tra peninsula, and the route to the site crosses a city of bridges, flyovers and tight junctions. Nobody priced the night moves or the escort.
The second problem is choice. Many central Vietnam projects can be served by a direct call at Da Nang port or by discharge in the south and a long road move north. The cheaper option on paper is not always the one that arrives on time. This guide is written by the desk that plans those moves for agents and contractors.
Da Nang port today means more than one quay. Since 1 July 2025, the former Quang Nam province is part of Da Nang city, so the Chu Lai port area in the south also sits inside the city. For planning, think of four areas.
| Area | Where | Status | What it means for project cargo |
|---|---|---|---|
| Tien Sa | Son Tra peninsula, at the mouth of Da Nang bay | Operating; main container and general cargo terminal of Da Nang Port JSC | Where most direct calls to Da Nang port discharge today, including flat racks and breakbulk |
| Song Han | On the Han river, in the city | Operating; small river terminal for ships up to about 5,000 DWT | Small coasters and barges only; not a heavy-lift berth |
| Lien Chieu | Northwest of the city, near the Hai Van pass | Shared infrastructure finished March 2026; container terminal construction started April 2026 | Future main cargo port of Da Nang; plan around it from 2027 onward, not for this year’s cargo |
| Chu Lai | Nui Thanh, south of the former Quang Nam province, now Da Nang city | Operating; developed by THACO, with a 50,000-ton berth | Serves the Chu Lai economic zone; useful for sites in the south of the merged city |
Sources: Wikipedia, Da Nang Port; Vietnam Government News, Lien Chieu container terminal; Viet Nam News, Chu Lai port. The Da Nang and Quang Nam port authorities were also merged into one Da Nang Maritime Port Authority from 1 August 2025, as VnEconomy reported.
Tien Sa port is the working heart of Da Nang port. Published figures list five berths with 965 m of quay, about 11 m navigation depth and a 450 m breakwater. A phase 2 upgrade finished in 2018 was designed to take ships of up to 70,000 DWT.
Volumes are growing. Tien Sa port handled about 850,000 TEU and more than 15 million tonnes in 2025, as Vietstock reported, and the port company targets more for 2026. The same port also receives cruise ships, so the yard and the gate are busy.
For frame sizes and payloads of the containers themselves, see our flat rack container dimensions guide and the open top container guide.
Lien Chieu is the new deep-water port of Da Nang, northwest of the city near the Hai Van pass. The city announced completion of the shared infrastructure, such as the breakwater and channel, in March 2026. Construction of the first container terminal, by a Hateco and APM Terminals consortium, started on 25 April 2026.
For a project shipping this year, Lien Chieu is not yet a port of discharge. Your cargo will still use Tien Sa port. What Lien Chieu changes is the longer plan: Tien Sa is expected to shift toward passenger and cruise traffic over time, while heavy cargo moves to Lien Chieu. For EPC contractors bidding on projects with deliveries in 2027 and later, the route survey should look at both ports.
Chu Lai port, in Nui Thanh, used to be “Quang Nam”. After the merger on 1 July 2025, it is inside Da Nang city, together with the Chu Lai open economic zone and its automotive and mechanical industry. THACO, which develops the port, has opened a 50,000-ton berth there and plans further expansion.
For project cargo, Chu Lai matters when the site is in the south of the merged city or in the Chu Lai economic zone. Discharging there instead of Tien Sa can cut a long road leg through Da Nang’s urban area. The question is the same as for any port: does a service with OOG acceptance call there for your sailing, and can the berth take the lift.

We say which port makes sense, which trailer, whether the road leg needs a permit and escort, and what it costs, so the rate you pass on is the rate you pay.
Da Nang city is about 960 km north of Ho Chi Minh City. Many cargo owners still bring central Vietnam project cargo in through Cat Lai or Cai Mep and truck it north, because more mainline services and more OOG space call in the south. Both routes work. The right one depends on the cargo and the site.
| Question | Points to a direct call at Da Nang port | Points to discharge in the south and road north |
|---|---|---|
| Sailing options | A carrier or a breakbulk ship calls Tien Sa or Chu Lai on your dates | Only mainline services in the south accept your flat rack or open top |
| Cargo size | Over-width, over-height or very heavy pieces, where every extra 100 km of permitted road adds risk | Standard OOG within normal permit limits, which travels long distances without trouble |
| Site location | Site in or near Da Nang, Hue or the Chu Lai zone | Site further south, closer to Quy Nhon or Nha Trang than to Da Nang |
| Container return | The flat rack can be returned in Da Nang within free time | The cargo can be transloaded from the flat rack in Ho Chi Minh City, so the frame goes back early |
| Customs | Clear at the port of discharge in Da Nang | Clear in Ho Chi Minh City, then move as domestic cargo |
A real example of the second route: in September 2026 we moved a large tank on a 40′ flat rack from Cat Lai port to a depot in Ho Chi Minh City, transloaded it to a lowbed, and trucked it to the Nhon Binh industrial cluster in Quy Nhon. The flat rack was returned in the south, and the tank travelled north on a trailer built for it.

For heavy cargo, the road leg from Da Nang port is where time and money go. A permitted oversize load runs only on the route and in the time window written on its permit, and in an urban area like Da Nang that usually means night moves.

These jobs come from our own records, with customer names left out. Our heavy-haul fleet is based in the south; in central Vietnam we run the plan, permit check and site supervision from our desk, with local partners where needed.
| Date | Cargo | Route and scope |
|---|---|---|
| Apr 2024 | 15 t of film and stage equipment | Customs, trucking, lashing, loading and airfreight for a TV production in Phu Cat, Binh Dinh |
| Aug 2025 | Precast concrete bridge girders | Night road moves in Da Nang (Cam Le, Hoa Vang bypass, Lien Chieu) to an overpass site, with police control and crane erection at site |
| Jul 2026 | 6 cable reels on two lowbeds | Road move from the south to Khanh Hoa, central Vietnam |
| Sep 2026 | Large tank on a 40′ flat rack | Cat Lai port → depot in Ho Chi Minh City → transload to lowbed → Nhon Binh industrial cluster, Quy Nhon |


This is what our desk checks before a truck leaves for Da Nang port or before a ship berths with project cargo.
We are a customs agent recognized by Vietnam Customs (Decision 247/QD-TCHQ, 26 February 2025), so the declaration, the inspection and the trucking sit with one desk. See our customs clearance guide for project cargo. Carrier local charges at Da Nang port differ by line; see our Vietnam local charges tables.
Cat Lai, Cai Mep, Hiep Phuoc, Haiphong and Da Nang compared for OOG and project cargo.
Vietnam ports →Six deep-water terminals in the south, mainline flat rack calls and the road leg to factories.
Cai Mep port →Lach Huyen vs the river terminals, published trucking rates and OOG jobs in the north.
Haiphong port →How we plan door-to-site moves for EPC contractors and agents.
Project cargo →We are a licensed customs agent (Decision 247/QD-TCHQ, 2025) and a member of WCA and OPCA; see our page for agents and our heavy haulage service.
Tony Tuan, CEO: WhatsApp +84 909 411 668 · ceo@projectshipping.vn
Nura Tu, Overseas Department: WhatsApp +84 906 770 650 · overseas@projectshipping.vn
Calling from Vietnam: 0909 411 668