☰ Menu

Insight · Heavy haulage · Updated November 2026

Lowbed Trailer Vietnam: Specs, Road Limits and Rates for Heavy Cargo

A lowbed trailer in Vietnam is the answer when your cargo is too tall for a flat rack on a container chassis or too heavy for a normal semi-trailer. The questions that decide your date are simple: which lowbed, how many axles, and does the loaded truck pass 2.5 m wide, 4.2 m high or 48 t gross.

Written by our heavy-haul desk in Ho Chi Minh City, which runs our own lowbeds every week. · Jump to the specs table

Lowbed trailer Vietnam: two Project Shipping 4-axle lowbeds carrying 3.8 m steel drums on an industrial park road in southern Vietnam
Two steel drums of about 3.8 m diameter on our two 4-axle lowbeds, Trang Bom → Chau Duc Industrial Park (March 2026).
Short answer: for lowbed trailer Vietnam moves we run our own fleet: one 6-axle lowbed with a 14.5 m deck, 3.2 m wide and rated up to 62 t, and two 4-axle lowbeds rated up to 44 t each. Loads beyond that go on hydraulic modular trailers or SPMT arranged through long-term partners. A loaded lowbed that passes the road limits needs an oversize or overweight permit, which takes about two working days once the file is complete.
62 tpayload of our 6-axle lowbed, 14.5 m deck
2 × 44 tour two 4-axle lowbeds
4.2 mroad height limit, deck included
2 hoursworking hours to a trucking plan once we have dimensions

What is a lowbed trailer, and when do you need one in Vietnam?

A lowbed (lowboy in the US) is a semi-trailer with a raised gooseneck at the front and a dropped deck behind it. The deck sits much closer to the road than a container chassis. That lower deck is the whole point: it buys you cargo height under the 4.2 m road limit.

In Vietnam you need a lowbed trailer in three common cases. Each one comes from a limit the agent can check from the packing list before booking.

  • Too tall for a flat rack: a 40′ flat rack on a container chassis puts the cargo floor high above the road, so a machine over about 2.4 m tall pushes the truck past 4.2 m. On a lowbed the same machine often stays under the line.
  • Too heavy for a flat rack: breakbulk pieces, tanks, presses or transformers above the payload of a flat rack go straight on the lowbed deck.
  • No container at all: loose cargo discharged from a breakbulk vessel, or cargo picked up at a factory, is loaded directly on the deck and lashed there.

A lowbed also carries containers when the box plus cargo is too high for a normal chassis. The photo below is one of our lowbeds with a 40′ open top at a terminal gate.

Project Shipping 4-axle lowbed trailer with company logo and phone number carrying a 40ft open top container at a port terminal gate in Vietnam
Our 4-axle lowbed with a 40′ open top at a terminal gate (2026). The company name and number on the gooseneck are ours.

Lowbed vocabulary agents ask about

  • Gooseneck: the raised front section over the tractor coupling. On our lowbeds it is about 4 m long and 1.6 m high.
  • Deck (well): the low loading platform between the gooseneck and the rear axles.
  • Axle lines: the number of axles under the trailer. More axles spread the load and allow more payload.
  • Prime mover: the tractor unit. It must be rated to tow trailer plus cargo by design; a permit never fixes an undersized tractor.

Lowbed trailer Vietnam specs: what we run

These lowbed trailer Vietnam figures are our own trailers, from our fleet register, not catalog figures. When the lowbed is ours, the date in our quote is a date we control.

EquipmentDeck and gooseneckPayloadTypical cargo
6-axle lowbed (own, 1 unit)Deck 14.5 m long, 3.2 m wide · gooseneck about 4 mUp to 62 tLong machinery, tanks, pressure vessels, several long breakbulk pieces on one deck
4-axle lowbed (own, 2 units)Deck about 12 m long · gooseneck about 4 m long, 1.6 m highUp to 44 t eachDrums, tanks, excavators, rollers, cable reels, over-height open tops
Prime movers (own)Heavy-duty tractor units matched to each trailerPer trailer and permitPort to site in the south, long-haul to central Vietnam
Modular trailers / SPMT (partners)Hydraulic axle lines, configured per loadPer configurationTransformers and single pieces beyond our lowbed range
Mobile cranes (partners)25–500 tn/aLoading and unloading where there is no port crane

Payload is the trailer’s rated figure on its inspection certificate. It is a hard ceiling: an overweight permit lets the vehicle use the road above the general limits, it never lifts the trailer’s own rating.

We tell you in the quote which equipment is ours and which comes from partners. For moves that need modular trailers, see our power transformer transport page.

Project Shipping prime mover and lowbed trailer carrying two 20ft open top containers at a warehouse in southern Vietnam
Two 20′ open tops on one of our lowbeds at a warehouse in the south (2026). The lowbed is not only for loose cargo.

Lowbed trailer Vietnam or flat rack chassis: which one?

The lowest-cost truck that passes the limits is the right one. A lowbed trailer Vietnam trip costs more per trip than a container chassis, so we only put cargo on a lowbed when the flat rack option fails on height, weight or length.

Your cargoUsual equipmentWhy
On a flat rack, under about 2.4 m tall, within FR payloadContainer chassisLowest cost; width over 2.5 m still needs a permit
On a flat rack or open top, too tall for a chassisLowbed with the container on the deckThe lower deck brings the top point back under 4.2 m
Loose piece up to about 44 t4-axle lowbedLow deck, our own trailer, short lead time
Loose piece up to about 62 t, or long pieces up to 14.5 m deck6-axle lowbedLonger, wider deck; more axles to spread the load
Heavier single pieces, power transformersHydraulic modular trailer or SPMT (partner)Axle lines added until each axle is within the bridge limits

If you are still deciding how the cargo leaves the origin port, read our flat rack container dimensions guide first. The choice of box at origin decides the truck at destination.

Not sure if it is a lowbed job?

Send L×W×H, weight and the pick-up and site. We tell you the truck, the permit class and the lead time within 2 working hours.

Lowbed trailer Vietnam road limits: width, height, length, weight

The road limits apply to the loaded vehicle, not to the cargo alone. They are set by Circular 12/2025/TT-BXD of the Ministry of Construction, amended by Circular 19/2026/TT-BXD from 1 July 2026 (Ministry of Construction notice).

LimitThreshold (vehicle + cargo)What it means for a lowbed
WidthOver 2.5 mOversize permit; most heavy lowbed loads pass this
Height from road to top pointOver 4.2 m (4.35 m for container vehicles)Oversize permit, plus a check of wires, signs and bridges on the route
LengthOver 20 mOversize permit; long pieces with rear overhang reach this fast
Gross weightOver 48 tOverweight permit, often a route survey and bridge check

Axle loads count too. A single axle is limited to 10 t, a tandem group to 11–18 t and a tri-axle group to 21–24 t depending on axle spacing. A heavy piece placed badly on the deck can break an axle limit even when the gross weight is legal.

Simple arithmetic for agents: tractor plus a 6-axle lowbed plus a 40 t piece is well over 48 t gross. Any loaded 6-axle lowbed near its rating will run on an overweight permit. Plan the lead time of every heavy lowbed trailer Vietnam move around it. The full permit process, documents and validity are on our oversize permit Vietnam page.

How tall can cargo be? Lowbed trailer Vietnam height check

Take 4.2 m and subtract the deck height. On our lowbeds the deck is roughly 1 m above the road, so cargo up to about 3.2 m tall usually keeps the loaded truck under 4.2 m without a height permit. We confirm the exact figure per unit, measured after loading, because tires, dunnage and cribbing all add centimeters.

Over that, a lowbed trailer Vietnam move is still possible. It needs an oversize permit, a route survey of wires and overpasses, and sometimes a night move with police coordination. The tallest loads we move in the south are drums and tanks of about 3.8–4 m diameter, which are far over the height and width limits.

1. Measure the cargoOverall L×W×H in mm from the packing list or drawing, plus the center of gravity if the piece is uneven.
2. Add the deck and dunnageDeck height plus timber or saddles under the piece gives the loaded top point.
3. Compare to 4.2 mUnder: normal lowbed move. Over: permit, survey and a lead time to match.
4. Check the gooseneckSmall pieces can ride on the gooseneck if piece height plus 1.6 m stays under the limit.
Process tank about 4 m in diameter strapped on a Project Shipping 4-axle lowbed trailer at a factory yard in Binh Duong, Vietnam
Process tank of about 4 m diameter on our 4-axle lowbed, ready to leave the fabricator, Dai Dang → Tan Dong Hiep (March 2026).

Why a 4 m tank still went on a 4-axle lowbed

For a tank like this, size decides the job before weight does. At about 4 m wide and well over 4.2 m loaded, the move needed its own permit, a route check and, under our rules, a lead and a rear escort car.

Weight picks the number of axles. Size picks the permit and the route.

Loading rules we apply on every lowbed

A lowbed trailer Vietnam move goes wrong at loading more often than on the road. These are the rules our crew works to before the truck leaves the gate.

  • Rear overhang up to 2 m, and never more than half the length of the piece. Longer pieces go on the 6-axle deck or a modular trailer.
  • Gooseneck space used with care: the gooseneck can take a few small, light pieces on multi-piece breakbulk lots. That often saves one truck.
  • Weight over the axles, not over the gooseneck: the heaviest point sits over the axle group, and the piece is centered side to side.
  • Lashing to the cargo’s lifting or lashing points with chains or straps rated for the load.
  • Re-measure after loading: the permit must match the real loaded width, height and weight. If it does not, the truck does not move.
  • Photos at every step: loading, lashing, departure and arrival, sent to you as the move runs.
Real load plan, October 2026: on a multi-piece breakbulk lot, the 6-axle deck took three pieces of 4.5 m each (13.9 m in a row) instead of two 4-axle lowbeds. A piece 3.35 m wide overhung the 3.2 m deck by only 7.5 cm per side. The total truck count did not fall, because the 6-axle lost the rear overhang space the lowbeds had, so the gain was cost per trip, not fewer trucks. This is the kind of trade-off we show you before booking.

Real lowbed trailer Vietnam moves in the south

Two recent lowbed trailer Vietnam jobs on our own trailers. Customer names are left out; routes, sizes and dates are real.

Steel drum about 3.8 m in diameter chained on a Project Shipping 4-axle lowbed trailer inside a fabrication workshop in Dong Nai

Two steel drums, about 3.8 m diameter

Cargo
Large steel drum shells, about 3.8 m across, one per truck
Route
Fabricator in Trang Bom, Dong Nai → plant in Chau Duc Industrial Park (March 2026)
Equipment
Our two 4-axle lowbeds and prime movers; partner mobile cranes at both ends
Challenge
Far over the width and height limits; loading inside the workshop at night
Result
Dedicated oversize permit per truck, route checked for wires, bridges and the plant gate; both drums delivered and lifted off

Process tank, about 4 m diameter

Cargo
Process tank, about 4 m in diameter
Route
Fabricator at Dai Dang → factory in Tan Dong Hiep, Binh Duong (March 2026)
Equipment
Our 4-axle lowbed and prime mover; partner truck crane for unloading
Challenge
Width and height far over the limits on a busy industrial corridor
Result
Own permit, checked route, lead and rear escort cars; unloaded at the receiving factory

The tank is the one pictured in the height section above. For more moves, including cable reels to Khanh Hoa and pressure vessels to the Cambodian border, see our heavy haulage Vietnam page.

Lowbed trailer Vietnam rates: how the price is built

We do not publish a flat lowbed tariff, and you should be careful with anyone who does. Two pieces of the same weight can need different trailers, permits and escorts. We price each lowbed trailer Vietnam move from the dimensions, and the quote shows every line.

Cost driverHow it changes the rate
Trailer class4-axle lowbed costs less per trip than the 6-axle; modular trailers are priced per axle line and day
Distance and roadKilometers, toll roads, and whether the permit forces a longer route around weak bridges
Permit classNo permit, a simple oversize permit, or an overweight permit with survey and bridge check
Escort and policeEscort cars for very wide loads; police coordination for night moves and difficult sections
Time windowsCity truck curfews and night-only moves add crew hours
LiftingPort crane, mobile crane at the site, or both; crane size follows weight and reach
Waiting timeTruck days waiting for cargo, customs or site access are charged per day

For a baseline, our public trucking table for standard 20′ and 40′ boxes from Hai Phong port starts at VND 2,100,000 per trip inside Hai Phong and reaches VND 12,700,000 to Nghe An (rates as of 11 October 2026, excluding VAT and lift-on/off). A lowbed trip on the same distance costs more. See the Haiphong port page for the zone table.

What you get from us is a net rate for network members, valid for a stated period, with the permit, escort and crane lines split out. If the measured cargo differs from the drawing, we tell you before the truck moves, not after delivery.

Ports where we pick up for lowbed moves

In the south we load lowbeds at Cat Lai, Cai Mep–Thi Vai and Ben Nghe ports, and at factories and fabricators across Dong Nai, Binh Duong and Ba Ria–Vung Tau. Many heavy pieces never see a port: they leave a local fabricator at night and reach the plant before the morning truck curfew ends.

Port-specific notes for flat racks and breakbulk are on our Cat Lai port guide and the breakbulk and heavy lift page.

Project Shipping prime mover and lowbed trailer with a red steel drum ready for a night move from a workshop in Dong Nai, Vietnam
One of the 3.8 m drums on our lowbed, ready for a night departure from the fabricator in Trang Bom (March 2026).

Send L×W×H + weight, pick-up and site. Get a lowbed plan and net rate within 2 working hours.

Add a drawing and the center of gravity if you have them. We reply with the trailer, the permit class, escort needs and an honest lead time.

FAQ: lowbed trailer Vietnam

What is the maximum payload of a lowbed trailer in Vietnam?
It depends on the trailer. Our 6-axle lowbed is rated up to 62 t and our two 4-axle lowbeds up to 44 t each. Heavier single pieces go on hydraulic modular trailers or SPMT arranged through partners.
Does a loaded lowbed always need a permit?
Only when the loaded vehicle passes a limit: 2.5 m wide, 4.2 m high, 20 m long, 48 t gross, or an axle limit. Most heavy lowbed loads pass at least one, so plan for a permit and about two working days after the file is complete.
How tall can cargo be on a lowbed before it needs a height permit?
Our lowbed decks are roughly 1 m above the road, so cargo up to about 3.2 m tall usually stays under 4.2 m. We confirm the exact figure after loading, because dunnage and tires change it.
Can a lowbed carry a flat rack or open top container?
Yes. When a flat rack or open top with its cargo is too tall for a normal chassis, we put the container on the lowbed deck to bring the top point down.
Are your lowbeds your own or rented?
The 6-axle lowbed and the two 4-axle lowbeds are our own, with our own prime movers. Modular trailers, SPMT and mobile cranes come from long-term partners, and the quote says so.
How much does a lowbed trailer cost in Vietnam?
There is no fair flat rate, because trailer class, distance, permit, escort, cranes and waiting time all change it. Send the dimensions and route and we return a net rate with each line split out within 2 working hours.
Will you contact my customer?
No. We work for you as the agent. Your shipment, your client.

Related reading

Oversize permit Vietnam

Limits, documents, lead times, validity and police escort.

Permit guide →

Heavy haulage in Vietnam

Our own lowbed fleet, route surveys and escort from port to site.

Heavy haulage →

Flat rack container dimensions

20′ and 40′ sizes, payloads and road height limits.

Flat rack guide →

Planning a lowbed trailer Vietnam move?

Send the dimensions, weight and route. We reply with the trailer, permit class and net rate within 2 working hours. We never contact your customer.

Tony Tuan, CEO: WhatsApp +84 909 411 668 · ceo@projectshipping.vn
Nura Tu, Overseas Department: WhatsApp +84 906 770 650 · overseas@projectshipping.vn
Network partners: agent page · Calling from Vietnam: 0909 411 668

Last updated: November 2026 · By Tony Tuan, CEO, Project Shipping

Request a quote Reply within 2 working hours · plan and net rate in one message

We use your details only to answer this request. We never contact your customer.

DOWNLOAD BẢNG GIÁ