Shipping Europe to Vietnam: Project Cargo and Breakbulk

Shipping Europe to Vietnam takes 30 to 60 days at sea, and a heavy piece can still lose a week after it lands. The usual causes are a terminal that cannot lift it, a truck permit written for the wrong height, or an origin statement that customs rejects. We run that Vietnam side for European forwarders.

For European forwarders, project freight agents, OEM shipping teams and EPC contractors. · Our real files from Italy

Shipping Europe to Vietnam: reach stacker lowering a 40 ft flat rack onto a Project Shipping lowbed at Cai Mep
A reach stacker lowers a 40′ flat rack onto our own prime mover and lowbed at TCTT, Cai Mep, for an international forwarder (March 2026).
55 daysGenoa sailing to ETA in Vietnam on our own LCL file, April to June 2026
580+shipments handled, March to September 2026
62 tpayload of our own 6-axle lowbed, 14.5 m deck
2 hoursVietnam-side quote within working hours once we have dimensions
WCA incl. WCA Projects · ID 135393 OPCA Gold · ID 75121659 Licensed customs agent · Decision 247/QĐ-TCHQ Est. 2017 · Ho Chi Minh City

European equipment arrives in Vietnam for factories, power plants and process lines. The sea leg is booked from Europe. What happens after discharge is decided in Vietnam: which berth, which crane, which trailer, which papers.

This guide to shipping Europe to Vietnam is written from the Vietnam end. It shows our own files from Italy, public transit times with their sources, the cranes at Cai Mep, the EVFTA origin rule, and the sum that decides your truck permit.

What shipping Europe to Vietnam looks like on our files

These are the Europe-loaded imports on our current system. Both are LCL machinery from Italy, which is a small sample, so we show them as working examples, not as a volume claim. Customer names are removed.

CargoTermsRouteVessel and dates
Coffee machines, 1,400 kg, LCL in a 40′ HC consolEXWGenoa (ITGOA) → Cat Lai, Ho Chi Minh CityYM Willpower 002E; sailed 22 April, ETA 16 June 2026
Machinery, 1,952 kg, LCL in a 40′ HC consolEXW, picked up near FlorenceScarperia (FI) → Genoa → Ho Chi Minh CityHMM Garam 022E; ETA 3 November 2026

Three lessons from these files apply to most plans for shipping Europe to Vietnam, including much heavier cargo:

  • EXW means the pickup is your problem. On the second file the cargo sat at a factory inland from Florence. An Italian partner handled the factory pickup, billed as a separate EXW line. Name who loads the truck at the factory before you quote EXW.
  • The LCL bill has four Vietnam lines. Both files carried THC, CFS, CIC and D/O at destination, billed by the co-loader’s office in Vietnam. Budget them on top of ocean freight. Our Vietnam local charges tables show how carriers set them.
  • Allow eight weeks, not five. Our April shipment took 55 days from sailing to ETA in Vietnam. That is longer than most rate sheets suggest.
Project Shipping prime mover with company name carrying a 40 ft flat rack under green tarpaulin out of Cat Lai port
Our prime mover with a 40′ flat rack under tarpaulin at the Cat Lai gate, part of a 12-container job to Phu My (March 2026).

How long does shipping Europe to Vietnam take?

Plan on about 30 to 45 days port to port from North Europe to Ho Chi Minh City, and up to 60 days with transfers or a Cape routing. Published figures disagree, so here is each one with its source.

LaneSea transitSource
Genoa → Cat Lai (LCL)55 days, sailing to ETAOur own file, April to June 2026
Rotterdam → Ho Chi Minh City (FCL)30 to 45 daysFreightAmigo route guide
Rotterdam → Hai Phong (FCL)35 to 50 daysFreightAmigo route guide
Hamburg → Ho Chi Minh City (FCL)35 to 45 daysFreightAmigo route guide
Hamburg → Hai Phong (FCL)45 to 60 daysFreightAmigo route guide

Container services that avoid the Red Sea and sail round the Cape add days to every figure above. Ask the carrier for the actual rotation and transfer port of your vessel, not a lane average.

Breakbulk and heavy lift vessels sail on their own schedules. A cargo that needs one should be fixed weeks ahead, and the Vietnam side must be ready before the vessel arrives. A new oversize road permit takes about 2 working days once documents are complete.

Send L×W×H, weight, port of loading and the site address in Vietnam. Get the discharge port, truck type, road permit check and a Vietnam-side net rate within 2 working hours.

For a tender, send the transport drawing and we add a route note and a transport budget.

Container, flat rack or breakbulk: which fits European equipment?

When shipping Europe to Vietnam, start from the largest piece as packed, with its lifting points and center of gravity. Then pick the equipment, and only then compare ocean rates.

Cargo from EuropeUsual equipmentWhat decides it
Spare parts, small machinesLCL or 40′ HC FCLFits inside; weight per box and floor load
Presses, CNC machines, tall crates20′ or 40′ open topLoaded from above; height over the box
Wide frames, skids, small tanks40′ flat rackWidth over the rack and rack payload
Mobile machinery, cranes on wheelsRo-RoCan drive or be towed on and off
Transformers, columns, turbines, long modulesBreakbulk on a heavy lift or multipurpose vesselWeight and length beyond any rack; crane reach at both ends

Rack sizes and payloads are in our flat rack container dimensions guide. For wheeled units, see Ro-Ro shipping in Vietnam. If you are weighing several flat racks against one breakbulk lot, our container vs breakbulk comparison sets out the trade-offs.

Project Shipping prime mover and empty lowbed trailer waiting in the yard at Cai Mep terminal for project cargo
Our prime mover and lowbed waiting in the yard at Cai Mep before a flat rack pick-up (March 2026).

Breakbulk and heavy lift into Cai Mep: what the port can lift

When shipping Europe to Vietnam with heavy breakbulk for the south, most cargo discharges in the Cai Mep–Thi Vai port area, a deep-water gateway south-east of Ho Chi Minh City. The terminal you discharge at decides the lift, so check its cranes before the vessel is fixed.

TerminalPublished dataFit for project cargo
PTSC Phu MyMain wharf 385 m, draft 14.5 m, vessels to 80,000 DWT; 2 × 40 t and 2 × 30 t Liebherr cranesGeneral and project cargo port; pieces over 40 t need ship’s gear or a mobile crane
TCITDraft at berth 16.8 m, vessels to 173,724 DWTMainline container services; flat racks and OOG units
TCTTDraft at berth 16 m, vessels to 166,000 DWTContainer services; our flat rack pick-ups in this guide
SSIT, Gemalink, CMITContainer terminals; ask us for current berth dataFlat racks and breakbulk packages on container services

Terminal figures as published by the operators; details and sources on our Cai Mep port guide.

  • Heavy lifts usually come down on ship’s gear. A piece above the shore crane limit is lifted by the vessel’s own cranes, then placed on a trailer under the hook or on the quay. Agree which one with the vessel operator and the terminal in advance.
  • Hook-to-truck saves a lift. If the trailer can stand under the hook, the piece goes straight from vessel to trailer. That needs the permit, trailer and escort ready on the day of discharge.
  • Modular trailers and SPMT through partners. For pieces beyond our lowbeds, we bring hydraulic modular trailers, up to 270 t per 6-axle trailer, and mobile cranes from 25 to 500 t through partners.

Pieces bound for northern Vietnam usually discharge at Hai Phong instead. River ports in Ho Chi Minh City take smaller vessels closer to the site. Our breakbulk and heavy lift in Vietnam page covers lifting plans and surveys in more depth.

Cai Mep, Ho Chi Minh City or Hai Phong: which port?

For shipping Europe to Vietnam, pick the port from the site and the heaviest piece, not from the lowest ocean rate. A cheap discharge at the wrong end of the country can cost more on the road than it saved at sea.

Vietnam portBest forWatch out for
Cai Mep–Thi VaiMainline services from North Europe and the Mediterranean, breakbulk and heavy lifts for the southLonger road leg to sites around Ho Chi Minh City; check the terminal on the arrival notice
Cat LaiLCL consols and flat racks for factories around Ho Chi Minh City and Dong Nai, as on our Genoa filesNight truck windows and a customs supervision step for flat racks and open tops
Tan Thuan, Ben Nghe, Lotus (Ho Chi Minh City)Breakbulk on smaller vessels; our trucks made 245 breakbulk and OOG moves from these ports in 18 monthsCrane booking, trailer access to the berth, discharge order
Hai Phong and Lach HuyenNorthern sites from Bac Ninh to Quang NinhLonger published transit from Europe than to the south

Our Vietnam ports overview compares every main gateway for OOG cargo.

EVFTA: how European cargo gets the lower duty rate

Goods of EU origin can enter Vietnam at the preferential EVFTA rate. The proof is a statement on origin written on the invoice by the exporter; above EUR 6,000 per consignment the exporter must be registered in the EU’s REX system. The EU does not issue an EUR.1 for exports to Vietnam.

  • Ask the exporter for the REX number early. Above the EUR 6,000 threshold the statement on origin must carry it. Without a valid statement, the importer pays the standard rate.
  • Use the exact wording. The text is fixed in the agreement’s origin protocol and the exporter signs it. The EU guidance on EVFTA origin has the text and the conditions.
  • Origin is not the port of loading. A machine made in Asia and shipped from Rotterdam is not EU origin. Check that the maker, the invoice and the B/L tell one consistent story.
  • Compare before you claim. Some machinery already has a low duty rate. Check the HS line first, then decide whether the statement is worth chasing. Our Vietnam HS code guide for machinery shows how to read the tariff line.

Import customs for project cargo from Europe

We clear imports under our own customs agent license, recognized by Vietnam Customs (Decision 247/QĐ-TCHQ, 26 February 2025). Filing runs on VNACCS, and each declaration lands in the green, yellow or red channel.

For project cargo, shipping Europe to Vietnam usually goes wrong at customs in one of four places:

  • Machines in many packages. A process line shipped unassembled needs its list registered with customs before the first import. Otherwise each package can be classified on its own, at its own rate.
  • Project duty exemption. Machinery that forms fixed assets of a qualifying investment project can be exempt from import duty. The investor registers the list with customs first, so start before the vessel sails.
  • Used equipment. Second-hand machinery from Europe must pass the age and proof test of Circular 56/2026/TT-BKHCN, in force since 5 September 2026. The general limit for HS chapters 84 and 85 is 10 years. Our import machinery to Vietnam guide has the full table.
  • Physical checks on large pieces. A heavy unit can be checked at the port even on a yellow channel. Plan waiting time, and keep the packing list and drawings ready.

The document list and channel steps are in our customs clearance guide for machinery.

How do you truck a European heavy lift out of the port?

Under Circular 12/2025/TT-BXD, as amended by Circular 19/2026/TT-BXD, a load needs a road permit when the loaded vehicle exceeds any of these limits. The official text of Circular 12/2025/TT-BXD has the full rules.

LimitOversize or overweight when
LengthOver 20.0 m
WidthOver 2.5 m
HeightOver 4.2 m (over 4.35 m for container vehicles)
Gross weightVehicle and cargo over 48 t

These limits apply to the truck and the cargo together, and they are where many plans for shipping Europe to Vietnam slip. A crate 3.6 m tall on a lowbed deck of about 1.5 m stands over 5 m from the road. That height decides the permit, the route and the bridges you can pass under.

  • Ports allow no tolerance. Terminals will not release cargo taller than the permit by even 1 cm, or heavier by even 1 kg.
  • We measure twice. Once before loading and again after lashing, with photos of the tape against the permit figures.
  • Ask for real lifting points. European drawings usually show them; send the drawing so we can plan the crane and the trailer position.
EquipmentCapacityTypical use
Own 6-axle lowbed62 t, 14.5 m deck, 3.2 m widePresses, tanks, long frames
Own 4-axle lowbeds (2 units)44 t eachMid-size machines, wide flat rack cargo
Hydraulic modular trailersUp to 270 t per 6-axle trailer, through partnersTransformers and heavy units beyond lowbed capacity
Mobile cranes and SPMTCranes 25–500 t, through partnersLifting at port, transloading and site installation
Mobile crane lifting a large red drum off a Project Shipping lowbed at a factory site in southern Vietnam
A mobile crane lifts an oversize drum off our lowbed at Chau Duc industrial park, southern Vietnam (March 2026).

Our heaviest single piece so far is 135 t. Route surveys and police escorts are covered on our heavy haulage in Vietnam page, and transformer moves on power transformer transport in Vietnam.

What drives the cost of shipping Europe to Vietnam?

Rates on this lane move with fuel, routing and vessel space, so we quote per enquiry and do not publish them. On heavy cargo, the Vietnam side can be a large share of the total cost of shipping Europe to Vietnam.

Cost elementWhat moves the price
Origin pickupEXW factory location, loading equipment, export clearance in Europe
Ocean freightContainer, flat rack or breakbulk; lost slots for OOG; routing and transfers
Destination local chargesTHC, D/O, CIC, CFS for LCL, set by each carrier or consolidator
Port handlingLifting, hook-to-truck or quay storage, customs supervision, storage after free time
CustomsDeclaration, physical check, origin proof, used-machinery inspection
Trucking, permit and escortDistance, size, weight, truck type, night windows, police escort
Duty and VATHS line, EVFTA statement on origin, project exemption

The fastest way to a firm number is the measured size and weight of each piece, the port of loading, the Incoterm and the site address.

How we work with European forwarders

European forwarders usually own the shipper and the sea leg of shipping Europe to Vietnam. We act as their Vietnam desk for discharge, customs, trucking and unloading.

1. Details inYou send the drawing or L×W×H and weight per piece, the port of loading and the site address.
2. Plan and rateDischarge port, lifting method, truck type, permit and a Vietnam-side rate within 2 working hours.
3. Before arrivalOrigin papers checked, permit applied for, crane and trailer booked, D/O arranged.
4. Discharge to siteClearance, pick-up, delivery and unloading, with photos to you at each step.
  • We never contact your customer for sales. Updates, photos and documents go to you unless you ask otherwise. Our flat rack jobs at Cai Mep in this guide ran for an international forwarder on exactly that basis.
  • Net rates for network members. We are in WCA (including WCA Projects) and OPCA; members get net rates on the Vietnam side.
  • One desk in Vietnam. Customs, trucking, permits and lifting sit with one team, so nothing falls between sub-contractors.

Partners can read our short page at projectshipping.vn/agents or download the company profile (PDF).

FAQ: shipping Europe to Vietnam

How long does shipping Europe to Vietnam take by sea?
Plan on about 30 to 45 days port to port from North Europe to Ho Chi Minh City, and up to 60 days with transfers or a Cape routing. Our own Genoa LCL file took 55 days from sailing to ETA in 2026.
Which Vietnam port should European breakbulk go to?
Cai Mep–Thi Vai for heavy lifts and mainline services to the south, river ports in Ho Chi Minh City for smaller vessels close to the site, and Hai Phong for northern sites. Check the terminal cranes before the vessel is fixed.
Do I need an EUR.1 for EU goods into Vietnam?
No. Under the EVFTA the EU exporter writes a statement on origin on the invoice, quoting its REX number when the consignment is above EUR 6,000. Without a valid statement, the importer pays the standard duty rate.
Can heavy pieces go straight from the vessel onto a truck?
Yes, if the permit, trailer and escort are ready on the day of discharge. The piece is lifted by ship’s gear or a mobile crane onto a trailer under the hook, which saves a second lift from the quay.
Do I need a road permit for oversize cargo in Vietnam?
Yes, when the loaded vehicle is wider than 2.5 m, taller than 4.2 m from the road, longer than 20 m or heavier than 48 t gross. A new permit takes about 2 working days once documents are complete.
Can you handle cargo bought EXW from a European factory?
Yes. Our Italian files were EXW, one collected from a factory near Florence by a partner in Italy. Tell us the pickup address and loading equipment, and we include the origin leg or work with your own European office.
Will you contact our customer in Vietnam directly?
We contact the consignee only for customs and delivery, as you instruct. We never contact your customer for sales. Updates and photos go to you.

Related pages

Breakbulk and heavy lift

Lifting plans, surveys and heavy units into Vietnamese ports.

Breakbulk in Vietnam →

Cai Mep port guide

Terminals, drafts, cranes and road legs for OOG cargo.

Cai Mep port →

Shipping Japan to Vietnam

Real Kobe excavator files, age limits and C/O forms.

Japan to Vietnam →

Shipping Korea to Vietnam

Busan transit days and C/O forms for heavy machinery.

Korea to Vietnam →

Project cargo in Vietnam

Our project cargo service from port to foundation.

Project cargo →

Shipping Europe to Vietnam with a piece that does not fit a standard box?

Tony Tuan, CEO: WhatsApp +84 909 411 668 · ceo@projectshipping.vn
Nura Tu, Overseas Department: WhatsApp +84 906 770 650 · overseas@projectshipping.vn
Calling from Vietnam: 0909 411 668

Last updated: November 2026